Goal Achievement · First-hand case study
From Two Months to 14 Days: How We Met the Handover Deadline
We had planned about two months to finish installing the mechanical, electrical, and plumbing (MEP) services in the annexes of a large aircraft maintenance hangar. When the main contractor handed over those areas to us late, we had just 14 days left. The client’s handover date was now at risk.
I was the project manager responsible for the electromechanical services. The annexes housed maintenance workshops, offices, classrooms, and support facilities. The 14 days were for the remaining MEP work in those areas, not the construction of the entire hangar. Even so, in that time we needed to finish the installation, test it, and deal with anything the tests turned up.
More people helped. Earlier testing made the difference.
I met with my engineers and foremen to explain how we would reorganize the work. We already had the materials we needed, so I decided to triple the skilled workforce and run two shifts. That gave us the people to carry out the installation in the time available. It didn’t solve the problem of what would happen if we found a fault near the end.
If we waited until every area was finished before we began testing, we could discover problems with very little time left to correct them. So I assigned four commissioning engineers to work alongside the installation teams. As soon as an area was ready, they carried out the necessary tests there while installation continued elsewhere.
This meant we could start finding and correcting problems while there was still time to act. The extra workforce helped us install faster. Changing the sequence of testing helped us avoid leaving all the corrective work until the end.
We had 14 days until handover, but I set an internal target of 12 days to leave two days for unforeseen problems or corrective work. We worked backwards from that target to set a realistic goal for each day. That gave us a clear way to check whether we were on track and adjust the next day’s work if we fell behind.
Each evening, we planned the next day room by room
At the end of each day, I met with the installation and commissioning engineers. They reported what had been done room by room: what had been installed, what had been tested successfully, and what needed corrective work the next day.
That level of detail mattered. A general progress update could tell us that installation was moving. A room-by-room review told us where work was actually ready and where we still needed to intervene. We used that information to plan the next day’s work while we still had time to make a difference.
We completed the remaining work within the 14 days and handed over the project to the client on time.
What I’d take into the next delayed project
Looking back through the BUILD360™ lens, the lesson is simple: when a deadline is under pressure, look at when you’ll find out whether the work is ready. If the first meaningful check happens just before handover, even a team that works faster can run out of time to fix what it finds.
For a milestone you’re responsible for, try writing down four things:
- What is the smallest part of the work we can check on its own?
- Who will check it, and how soon after it is ready?
- What evidence will tell us it is ready for the next person or team?
- If the check finds a problem, who will act on it, and when will we review it again?
Start with one part of the work. The aim is to find out what needs fixing while you still have time to fix it.